Charging Scheme
HPC Phase II Intelligent Computing Cluster
Price for accessing computing resources in the queue
Resource Type | Shared (Official) | Exclusive (Official) | Emergency (Official) | Debug Pricing |
---|---|---|---|---|
CPU | CNY 0.02/core/hour | CNY 0.04/core/hour | CNY 0.06/core/hour | Free |
GPU (A800) | CNY 1.60/GPU/hour | CNY 2.50/GPU/hour | CNY 4.00/GPU/hour | Free |
GPU (A30/A40/Ascend) | CNY 0.50/GPU/hour | CNY 1.00/GPU/hour | CNY 1.50/GPU/hour | Free |
Notes:
- For GPU resources with MIG mode enabled, the GPU cost for a job will be calculated based on the requested memory capacity.
- The runtime of a job/container is calculated based on the actual start and end times. If the runtime is less than one hour, it will be calculated in seconds.
- "Shared" corresponds to low priority, "Exclusive" corresponds to medium priority, and "Emergency" corresponds to high priority.
- Based on the pricing, specify the relevant queues to use:
CPU Shared: (i64m512u, i64m512r, a128m512u, long_cpu, i96m3tu)
CPU Exclusive: (i64m512ue, i64m512re, a128m512ue, i96m3tue)
CPU Emergency: (emergency_cpu)
GPU (A800) Shared: (i64m1tga800u, long_gpu)
GPU (A800) Exclusive: (i64m1tga800ue)
GPU (A800) Emergency: (emergency_gpu)
GPU (A40) Shared: (i64m1tga40u)
GPU (A40) Exclusive: (i64m1tga40ue)
GPU (A40) Emergency: (emergency_gpua40)
Price for server leasing
Resources Type | Pricing |
---|---|
CPU Server (Intel 64 cores) | CNY 62.00/unit/day |
CPU Server (AMD 128 cores) | CNY 123.00/unit/day |
Big CPU Memory Server | CNY 62.00/unit/day |
GPU Server (8 A800) | CNY 480.00/unit/day |
GPU Server (8 A30/A40/Ascend) | CNY 192.00/unit/day |
Notes: For leasing periods less than 1 day, the calculation will be based on 1 day.
Price for storage resource
Storage Type | Free Capacity | Pricing Beyond Free Capacity |
---|---|---|
HDD | 1TB/user | CNY 0.50/1TB/day |
SSD | 200GB/user | CNY 0.50/100GB/day |
Notes:
Storage usage is collected from 0:00 to 1:00 daily.
Beyond the free capacity, HDD storage usage below 1TB is charged as 1TB, and SSD storage usage below 100GB is charged as 100 GB.
In the future, further measures of storage capacity management will be considered based on the usage of storage resources.
HPC Phase III (ACD) Intelligent Computing Cluster
Free during the trial period.